Cambodia Water Security Improvement Project · P176615

Results Framework

Project Development Objective

To build the foundation for improved water security in Cambodia and increase agricultural productivity in the selected river basins, and to provide immediate and effective response in case of an Eligible Crisis or Emergency.

Every figure on this page is from PAD5093, the project appraisal document of 30 May 2024. Nothing here is a platform estimate.

Indicators and targets

Sixteen indicators — three at the level of the Project Development Objective and thirteen across Components 1 to 4. Component 5, the contingent emergency response, has none by design.

Scroll sideways for later periods.

No values have been reported yet. Reporting and verification are the next part of this module to be built.

Indicator definitions

What each indicator actually measures, how often, from which source and by what method — the PAD’s monitoring and evaluation plan, pages 37 to 40. These are the answers to the questions someone asks when told to report a figure.

Components

Budgets in millions of US dollars, IDA. The total is US$145 million, SDR 110.1 million.

The results chain

How the project is put together, from its objective down to the activities the appraisal document says will be financed. Everything here is from PAD5093; nothing is inferred.

The PAD describes activities under sub-components and indicators under components, and never joins the two. Which activity moves which indicator is for MOWRAM’s M&E Unit to state, so the platform leaves that link empty rather than guessing it.